Fieldway worked with Kier Group to provide temporary electrical supplies and lighting during the phased construction of a 71,000 sq ft C.R. Laurence facility.
The works progressed alongside numerous contractors from groundworks and steelwork through to completion. Fieldway installed temporary electrics and lighting within the steel framework, returned regularly during a 14-week phase to adapt supplies as required, then stripped out the temporary systems without disrupting the final stages of construction. The project was delivered on time and without additional cost to the client.
What we did
Fieldway delivered phased temporary electrical installations across a 71,000 sq ft construction site for Kier.
Development size (sq ft)
71000
Main installation phase
14
weeks
Key construction phases
3
Fieldway worked alongside multiple contractors throughout the construction programme, adapting temporary supplies and lighting as the development progressed.
Resident Care and Communication
Phased delivery helped maintain safe and efficient construction activity across the busy site.
Fieldway delivered the works in phases, attending site regularly to install new supplies and lighting as required before systematically removing equipment at the end of the project.
Challenges
The temporary electrical system had to evolve alongside multiple construction phases and contractors.