Fieldway delivered passive fire protection works at Carey Lodge, Cherry Garth and Icknield Court for Housing Solutions. Following Fire Risk Assessments undertaken by an external consultant, Fieldway completed detailed compartmentation surveys and fire door inspections to identify required remedial works.
The programme included fire curtains, fire barriers, penetration sealing and multiple FD60 fire doors. Rockwool sealant was used for fire stopping works. Following completion, Fieldway provided a post-inspection report and O&M manual, demonstrating the completed works and supporting compliance requirements.
What we did
Fieldway delivered passive fire protection works across three Housing Solutions properties in Berkshire.
Detailed surveys established the required scope before remedial works commenced, ensuring solutions were targeted to identified fire safety risks.
Resident Care and Communication
Our survey-led approach provided clear solutions while minimising unnecessary works.
Properties
3
+
Fire door rating
FD60
Fieldway completed detailed compartmentation surveys and fire door inspections following external FRAs. The findings established precise remedial requirements and provided the basis for a compliant, evidence-led programme.
Innovations, Challenges, Solutions
Existing fire safety risks required detailed investigation before remedial works could be defined.