A close-up of a Vaillant aroTHERM plus Air Source Heat Pump (ASHP) unit, professionally installed for a residential property against a red brick wall.
Home | Case study | Residential Air Source Heat Pump Installation

Residential Air Source Heat Pump Installation

Sector

Social Housing

Location

East of England

Service

Decarbonisation

Axis undertook a residential air source heat pump (ASHP) installation for our client Eastlight Community Homes for social housing residents in Braintree, Essex. This initiative aimed to reduce energy consumption and energy bills for residents.

Eastlight Community Homes

Our residential air source heat pump installation, enhanced energy efficiency and comfort for social housing residents

Project Details

The properties, owned and managed by Eastlight Community Homes, included three family homes and one bungalow housing an elderly resident. The previous system was outdated, lacked advanced controls, and operated inefficiently, often creating excessive noise.

We began with thorough property surveys, focusing on heat loss, radiator capacity, and pipework requirements. Performance projections were developed based on Energy Performance Certificate (EPC) data, enabling us to create a custom design. This included enhanced heating zones, expanded pipework and larger radiators to support efficient heating distribution.

Our M&E team removed the outdated ASHP units and replaced them with state-of-the-art equipment, including the Vaillant aroTHERM ASHP, uniSTOR heat pump unvented cylinder, buffer unit and sensoCOMFORT controls. These modern features include remote access, real-time temperature sensors, and thermostats for improved usability. We also installed Grundfos pumps and Honeywell valves to ensure long-term reliability and performance.

The new ASHP system, with a high Seasonal Coefficient of Performance (SCOP) at a 45°C flow temperature, offers efficient heating and hot water with real-time control adjustments. This reduces energy usage, cutting heating costs by an estimated 1,400 kwh annually.

Benefits

  • Minimised energy consumption
  • Reduced energy bills
  • Future proofing
  • Uninterrupted heating and hot water service
  • Reduced carbon footprint

Residential Care

Our team kept in regular contact with our residents before and during works, we also had a supervisor on-site to communicate and answer any questions raised.

Client Relationship

Under the 2-year renewables contract with an indicative value of £500,000 per annum, we will be decommissioning existing oil, gas and electric systems and installing new Air Source Heat Pump (ASHP) systems. Since September 2023, we have completed a total of 6,114 services. At an Eastlight Community Homes property, we celebrated installing our 100th ASHP!

Specifications

  • Strip out and removal of unit
  • Fit unvented cylinder
  • Build new concrete base for new unit
  • Fit out internal pipework
  • Electrical works
  • New ASHP installation

It was all good, professional and friendly we were always pre warned about work since the install. It’s been very warm here, best we have had in the 11 years we’ve been here

Fieldway

Planned repairs services

Looking for more information about Axis’ repair services? Click below to find out more.

0151 480 9909
enquiries@fieldway.co.uk

Please enter your first name

Please enter your surname

Please enter a valid email address

Please add description of enquiry

Please agree to the terms*

Thank you! Your form has been successfully submitted. Someone will be in touch with you soon.

Error sending form.

View or share this case study

You may also be interested in...

Capital Shopping Centres – Fire Protection and Structural Encapsulation

Fieldway delivered 30,000m² of passive fire protection at operational Eldon Square shopping centre in Newcastle.

Steel girders under white arch

The Mall Blackburn – Fire Protection and Insulation

Fieldway delivered passive fire protection and 4,700m² of soffit insulation at The Mall Blackburn shopping centre.

Kier Construction Ltd – Electrical Installation

Fieldway delivered phased temporary electrical installations for Kier across a 71,000 sq ft C.R. Laurence development.

Salford City Council – Fire Alarm Upgrade

Fieldway upgraded the fire alarm system at the 20-bed Barton Moss Secure Care Centre for Salford City Council.

Wythenshawe Community Housing Group – Fire Alarm Upgrade Programme

Fieldway upgraded fire alarm systems across nine 16-storey Wythenshawe Community Housing Group blocks in South Manchester.

PA Housing – Fire Safety Maintenance and Compliance Programme

Fieldway delivers a seven-year fire safety maintenance programme for PA Housing across Nottingham, Derby and Leicester.

Battersea Power Station Development Company – Fire Stopping and Acoustic Sealing

Fieldway delivered specialist passive fire and acoustic sealing works within the iconic Battersea Power Station redevelopment in London.

Jigsaw Homes Group – Fire Compartmentation and Passive Fire Remediation

Fieldway delivers passive fire remediation and compartmentation surveys for Jigsaw Homes across its national property portfolio..

Transport for Greater Manchester – Fire and Electrical Compliance

Fieldway maintains fire and electrical systems across 28 Transport for Greater Manchester sites throughout Manchester.

Fire door, brick wall, red fire extingusher

E3 Cube – Schools and Academies Fire Safety Improvement

Fieldway delivered fire safety improvements across five schools and academies in the North of England with E3 Cube.

Wirral Borough Council – Lingham Primary School Fire Alarm Upgrade

Fieldway upgraded the fire alarm system at Lingham Primary School in Moreton for Wirral Borough Council.

Your Housing Group – Major Property Electrical Inspection Programme

Fieldway completed 4,000 EICRs across Your Housing Group’s portfolio, including C1 and C2 electrical remedial works.

BAM Construction – Site Set-Up and Building Fit-Out

Fieldway provided BAM Construction with site set-up and fit-out support across two Manchester city-centre construction projects.

Cobalt Housing – Fire Safety Servicing, Maintenance and Upgrades

Fieldway delivers fire safety servicing and fire alarm upgrades across 960 Cobalt Housing properties in Liverpool.

Mosscare St Vincent’s – Fire Door FRA Remedials

Fieldway delivers fire door remedial works for Mosscare St Vincent’s following Fire Risk Assessment recommendations across the North West.

Johnnie Johnson Housing – Compartmentation and Fire Doors

Fieldway delivered compartmentation, fire door and FRA remedial works across more than 80 Johnnie Johnson Housing properties.

Housing Solutions – Fire Compartmentation and Fire Door Remediation

Fieldway delivered passive fire protection and fire door remediation across three Housing Solutions properties in Berkshire.

operative in high vis testing an electrical outlet

Together Housing – Electrical Inspection and Compliance

Fieldway completed EICRs and remedial electrical works across 985 Together Housing properties in Yorkshire and Lancashire.

Countess of Chester Hospital – Fire and Security Alarm Replacement

Fieldway is replacing fire and security alarm systems within the live healthcare environment at Countess of Chester Hospital in Chester.

operative in orange high vis vest testing newly installed alarm system

Southway Housing Trust – Fire Safety and Building Systems Maintenance

Fieldway maintains fire and building systems across 6,000 Southway Housing Trust properties throughout Manchester.